Walnut Creek Linear Trail Updates

  1. Current Development
  2. Trail Segment Overview

IN PROGRESS: PHASE 3B (Cannon/Carlin intersection to Oliver Nature Park)

  • Planning stages began January 2022
  • Widen sidewalks and create safe crossings for trail along Cannon and Matlock Roads to the Oliver Nature Park entrance

IN PROGRESS: 4A (Town Park to Mans Best Field Dog Park)

  • Construction completed in Spring 2022 on the paved, 12-ft wide trail connecting the existing trail at Town Park under the Main St./157 Bridge heading west
  • Will connect to future 4A expansion to Mans Best Field Dog Park; planning underway on those segments

COMPLETE: 3A (McKnight Park East to Cannon/Carlin Roads)

  •  Construction began February 2021, completed December 2021
  • One-mile paved, 12-ft wide trail from the rear of McKnight Park East, around the Shops at Broad development to connect with existing sidewalks at Cannon and Carlin Roads

trail phases 2022